Raslan, on a field visit to the Kafr Dawood Sadat Link, in the presence of the Governor of Menoufia and the Director of Menoufia Security

16/01/2021

Within the framework of the Ministry of Transport’s plan represented by ENR concerning the establishment of new lines and connections in order to connect the new urban communities to the railway network for serving the transportation of passengers and freight.

Today, Saturday, January 16, 2021, Eng. Ashraf Raslan, ENR’s Chairman, paid a field visit to Kafr El-Daward / AL-Sadat connection in the presence of the Major General, Governor of Menoufia, and the Major General, Director of Menoufia Security. The visit aimed to follow up the removal of trespassing from the beginning of the line at Kafr El-Daward station, follow up the completion of civil works as well as the start of bridges construction works from 0 km point to 2,500 km point in implementation of Public Benefit Resolution No. 1735 of 2020 where the General Nile Company for Roads Construction are carrying out the works.

It is worth noting that all civil works in the project were completed for the distance from 19,500 km point to 34,400 km point. A terminal station for passengers and freight was established at 34.00 km point, and a passengers terminal was established at 28 km point. Bridges, cladding works, block booths and a metal bridge were constructed on Rayah El Nassery at 2,500 km point.

In this respect, coordination is currently being made with the Survey Directorate in Menoufia Governorate and the security bodies to implement Public Benefit Decision No. 1736 of 2020 for the distance from 2,500 km point to 19,500 km point and to secure work crews during the implementation along the corridor from 0 km point to 19,500 km point.

Eng. Ashraf Raslan ended the visit by inspecting the iron connection works from 19,500 km point until the end of the connection at 34,400 km point, including the building of the two stations at 28 km point & 34.00 km point in Al-Sadat City.